The City of Gillette, Purchasing Division, opened bids for this project at the City Warehouse on Tuesday, April 2, 2019 at 2:30 P.M.
The following table summarizes the bids received and the Engineer's Estimate.
BIDDER
|
TOTAL BID
|
Hot Iron, Inc.
|
$811,670.47
|
LJS Concrete & Excavating
|
$814,711.23
|
DRM, Inc.
|
$1,050,440.00
|
Engineer’s Estimate (HDR)
|
$1,010,802.00
|
BID IRREGULARITIES
The three bidders on the project were Hot Iron, Inc., LJS Concrete & Excavating, and DRM, Inc. All bids were submitted on time and had the required Bid Bond. All three bids also included a Residency Certificate. No irregularities were found that would justify rejection of a bid.
Based on the above evaluation, HDR recommend that the City of Gillette award the project to Hot Iron, Inc. at the bid amount of $811,670.47.
CONSTRUCTION ESTIMATE
The total construction cost for this project was estimated at $1,010,802.00 and was prepared by HDR. The low bid received from Hot Iron, Inc. was $811,670.47, approximately 19.7% or $199,131.53 lower than the Engineer's Estimate.
BUDGET
The funding for this project has been allocated from the 1% Optional Sales Tax Account 201-10-05-419-70-47420 and is fully funded.
CONTRACTORS REVIEW
Hot Iron, Inc. has no apparent problems with their bid.
Bid Tabulation is attached. |