The City of Gillette, Purchasing Division, opened bids for the project at the City Warehouse on Tuesday, April 23, 2019 at 2:00 P.M..
The following table summarizes the bids received and the Engineer’s Estimate.
Bidder
|
Total Bid
|
GW Construction
|
$107,721.50
|
Broken Link Construction, LLC.
|
$115,157.10
|
Simon Contractors
|
$162,053.00
|
Croell, Inc.
|
$ 133,124.00
|
Engineer’s Estimate
|
$ 145,171.00
|
BID IRREGULARITIES: No bid irregularities were found. All four (4) bids were received on time, Proper Bid Security in the form of Bid Bonds for Five percent (5%) of the bid amounts was included with all the bids. All bids included a “Certificate of Residency Status.”
There was a quantity discrepancy on one bid item between the electronic bid tab and the printed bid tab. The discrepancy does not change the bidding outcome.
CONSTRUCTION ESTIMATE: The total construction cost for this project was estimated at $145,171.00 and was prepared by the City of Gillette Engineering Division. The low bid from GW Construction was $107,721.50, approximately 25.8% lower than the Engineer’s Estimate.
Budget: The funding for this project has been allocated for the 1% Optional Sales Tax Account 201-10-05-419-44331. |