Approval Sheet

CITY OF GILLETTE
201 E. 5th Street
Phone (307)686-5200
CITY OF GILLETTE


www.gillettewy.gov

 
DATE: 10/15/2019 7:00:00 PM
SUBJECT:
Council Consideration of a Professional Services Agreement for Design and Bidding Services Associated with the 2020 Water Main Replacement Project, with Morrison Maierle, Inc., in the Amount of $440,000.00 (1% Project).
BACKGROUND:

This contract will consist of design and bidding services to complete the 2020 Water Main Replacement Project.  The areas that have been identified and prioritized for this water main replacement are as follows:

1.  E. 3rd Street from Hwy 59 to Gurley Avenue.

2.  E. 4th Street from Hwy 59 to Gurley Avenue.

3.  E. 5th Street from Hwy 59 to Gurley Avenue.

4.  E. 6th Street from Hwy 59 to Gurley Avenue.

5.  E. 7th Street from Hwy 59 to Gurley Avenue.

ACTUAL COST VS. BUDGET:
The cost for this Design and Bidding Professional Service Contract is $440,000.00 which is 10.2% of the estimated construction cost of $4,300,000.00 for the 2020 Water Main Replacement Project.  The contract will be funded from the 1% Optional Sales Tax Fund Account #201-10-05-419-70-47410 which has $5,700,000.00 budgeted for this project.
SUGGESTED MOTION:
I move for the Approval of a Professional Services Agreement for Design and Bidding Services Associated with the 2020 Water Main Replacement Project, with Morrison Maierle, Inc., in the Amount of $440,000.00 (1% Project).
STAFF REFERENCE:
MAP/VIDEO - Ry Muzzarelli, P.E., Development Services Director
ATTACHMENTS:
Click to download
Agreement
Site Map