G & G Landscape, Inc. was awarded a bid of $488,884.00 and completed the work for a cost of $531,798.66. There was a total of four (4) change orders on the project.
Change Order #1 - $3,300 – Provided for maintenance mowing during the project as well as installation of hardline Cat-5 Ethernet connectivity from the City Hall Telecommunications room to the new Calsense Irrigation controller, replacing the original cell modem communication method.
Change Order #2 – $6,996.00 – Provided for the installation of approximately 1,800 square feet of concrete apron installed along the north and west sides of the City Hall Building at the request of the Facilities Maintenance Division. The cost of this concrete work was offset by reducing the number of plants and related irrigation originally specified in the design.
Change Order #3 - $20,698,50 – Provided for the removal and replacement of approximately 450 square feet of concrete paving at the west parking lot entrance of City Hall. Also replaced weather damaged ADA sidewalk ramps and sidewalk panels.
Chane Order #4 – $11,911.16 – Provided final quantity reconciliation per pricing provided in Change Orders #2 and #3. Provided for clearing, grubbing and mulch installation in the City Hall Parking Lot center median as well as additional mulch rings on existing trees on the northwest corner of the property. This project was fully funded from the 1% Optional Sales Tax Fund. |