The City of Gillette, Purchasing Division, opened bids for this project at the City Warehouse on Thursday, January 31, 2019 at 2:30 P.M..
The following table summarizes the bids received and the Engineer's Estimate.
BIDDER
|
TOTAL BID
|
LJS Concrete and Excavation
|
$758,203.00
|
Wyoming Earthmoving Corporation
|
$756,475.94
|
JR Civil
|
$741,733.07
|
Hot Iron, Inc.
|
$617,866.19
|
Mountain View Builders
|
$548,628.00
|
Engineer’s Estimate
|
$799,750.00
|
BID IRREGULARITIES:
The five bidders on the project were LJS Concrete & Excavation, Wyoming Earthmoving Corporation, JR Civil, Hot Iron, Inc., and Mountain View Building, Inc.. All bids were submitted on time and had the required Bid Bond. All bids included a Residency Certificate and acknowledged Addendum #1.
CONSTRUCTION ESTIMATE:
The total construction cost for this project was estimated at $799,750.00 and was prepared by DOWL. The low bid from Mountain View was $548,628.00, approximately 31% lower that the Engineer's Estimate.
BUDGET:
Monies for this project have been budgeted from the 1% Optional Sales Tax Fund #201-10-05-419-70-47420 in the amount of $1,600,000.00.
CONTRACTOR'S REVIEW:
Mountain View Builders has no apparent problem with their bid.