Bids were opened and read aloud on March 5, 2019 at the City of Gillette Purchasing Division. Two (2) bids were received on the project.
The bid results are as follows:
Black Cat Construction |
$58,317.00 |
Wyoming Earthmoving Corporation |
$93,079.56 |
The Engineer's estimate, prepared by Inberg-Miller Engineers, was in the amount of $112,083.00
The funding for this project has been allocated from the 1% Optional Sales Tax Account 201-10-05-419-40-44331 in the amount of $160,000.00
It is recommended that the bid in the amount of $58,317.00 be awarded at this time.
|