Approval Sheet

CITY OF GILLETTE
201 E. 5th Street
Phone (307)686-5200
CITY OF GILLETTE


www.gillettewy.gov

 
DATE: 3/19/2019 7:00:00 PM
SUBJECT:
Council Consideration for the Acceptance of Public Improvements for the Gillette Madison Pipeline Project, Contract 8, Installed by COP Wyoming, in the Amount of $7,099,574.24.
BACKGROUND:

This project included the installation of 31,615 lf of 18" PVC transmission line and appurtenances for the purpose of delivering water produced and treated from the City of Gillette's Fort Union and Fox Hills wells to the blending facility located near the WYODAK power plant.

Burns & McDonnell Engineering Co. provided services to perform all necessary bidding, construction administration, inspection, materials testing, and other construction phase services directly related to construction for this project.  They provided the attached recommendation for award.

ACTUAL COST VS. BUDGET:

The original contract amount for this project was $6,975,990.00.  There were three change order for a net added cost to the project of $123,584.24.  Below is a summary of these change orders:

Change Order

Description

Contract Time

Amount

01

Removal of electrical conduit; WYDOT fencing modifications; alignment modifications; Sprigler property delays; Interstate bore obstruction

63

$151,806.30

02

Badger Avenue mill and overlay

12

$69,920.78

03

Final Quantity Adjustments

0

($98,142.84)

 

TOTAL

+73

$123,584.24

COP Wyoming was unable to finish the project within the allotted contract time, resulting in liquidated damages deducted from payments for a total amount of $107,554.29.

Budget Account No.  301-70-72-441-70-47411

Project No. 07EN58
SUGGESTED MOTION:
I Move for Approval for the Acceptance of Public Improvements for the Gillette Madison Pipeline Project, Contract 8, Installed by COP Wyoming in the Amount of $7,099,574.24.
STAFF REFERENCE:

PHOTOS/MAP - Michael H. Cole, P.E., Utilities Director

 

ATTACHMENTS:
Click to download
Engineer's Recommendation
Warranty
Affidavit on Behalf of Contractor
Certificate of Final Completion
Map