Project Description:
This project will consist of installation of new, as well as failed, electrical service drops at necessary locations for the electric utility as well as other similar needs for the other City departments and divisions.
Bid Opening:
Bids for this project were opened on June 5, 2019 at 10:00 A.M. at the office of the City Purchasing Division, Central Warehouse, 800 North Burma Avenue, Gillette, Wyoming. Contract bid documents were received from one bidder. The bid evaluated costs are shown below:
CONTRACTOR BID EVALUATED COSTS
ProElectric, Inc. $1,565.00
The evaluated total shown above is based on a formula set for the purpose of bid evaluation only. A copy of the bid tabulation is attached for your review. Actual costs and number of services to be installed for the 2019/20 budget year is estimated at:
$635 per service @ 50 services = $31,750
This is a 12.7% increase over last year. |