DATE:
|
8/20/2019 7:00:00 PM |
SUBJECT: |
Council Consideration for the Acceptance of Public Improvements for the Winland Industrial Park Water and Sanitary Sewer Improvements Project, Installed by Hot Iron, Inc., in the Amount of $1,016,130.28 (1% Project). |
BACKGROUND: |
This project upgraded the Winland Industrial Park water and sanitary sewer system to City standards. This was accomplished by replacing 1118 LF of 8-inch sanitary sewer main between five different locations, the installation of 549 LF of new 12-inch water main, the installation of 31 meter pits, and installation of 5 additional fire hydrants. |
ACTUAL COST VS. BUDGET: |
There were six (6) change orders associated with this project that increased the contract by $99,785.00, resulting in a final contract amount of $1,016,130.28 from the original amount of $916,345.22.
Change Order
|
Description
|
Contract Days Added
|
Force Account Amount
|
Contract Amount
|
1
|
Additional 26 Frames, Covers, and Concrete Collars for Meter Pits in Drive Areas
|
7
|
$20,882.68
|
$0.00
|
2
|
Additional 43.5 SY of 8” Concrete Paving for Water Main Connection.
|
0
|
$4,785.00
|
$0.00
|
3
|
Additional Base Course for Soft Repair, Fire Hydrant Extensions, Water Valve box, and Honnen Equipment 1” Water Service Extension.
|
17
|
$24,332.32
|
$5,296.74
|
4
|
French Drain near Winland Carwash and raise meter pit at Block 1, Lot 9
|
1
|
$0.00
|
$2,901.18
|
5
|
Dewatering around existing Manhole on Winland Drive
|
2
|
$0.00
|
$2,093.60
|
6
|
Final Quantity Adjustments
|
0
|
$0.00
|
$89,493.54
|
|
Total
|
27
|
$50,000.00
|
$99,785.06
|
|
SUGGESTED MOTION: |
I move for Approval of the Acceptance of Public Improvements for the Winland Industrial Park Water and Sanitary Sewer Improvements Project, Installed by Hot Iron, Inc., in the Amount of $1,016,130.28 (1% Project). |
STAFF REFERENCE: |
MAP/VIDEO - Ry Muzzarelli, P.E. Development Services Director |
|
|