DATE:
|
8/27/2019 7:00:00 PM |
CASE NUMBER AND TITLE: |
19.025V - 1509 Boise Avenue Easement Vacate |
APPLICANT/OWNER: |
Kari Outzen |
AGENT: |
Dick Doyle, Doyle Surveying, Inc. |
CASE SUMMARY: |
The owner, Kari Outzen, is seeking approval to vacate 4’ of a 15’ easement located on the west of Lot 5, Block 2, Northland Village Mobile Home Park, First Filing, Phase III. |
CASE BACKGROUND: |
The owner, Kari Outzen, is seeking approval to vacate the easterly 4’ of a 15’ Utility easement for the purpose of constructing an accessory garage. The easement is located on the west of Lot 5, Block 2, Northland Village Mobile Home Park, First Filing, Phase III. The proposed plot plan indicates the existing utilities will be accessible through the remaining 11’ General Utility Easement with at least 5' remaining on the east side to accommodate the existing gas line.
A locates request indicates the proposed 4’ vacate area is free of existing utilities. |
STAFF RECOMMENDATION: |
Staff recommends approval, subject to all Planning Requirements. |
CASE MANAGER: |
Clark Sanders, Planner |
TENTATIVE CITY COUNCIL DATE: |