SUBJECT:
Council Consideration for the Acceptance of Public Improvements for the Wastewater Treatment Facility Anaerobic Digester Cleaning and Coating Project to R.C.S. Construction, Inc., of Rapid City, South Dakota, in the Amount of $470,737.87.  
BACKGROUND:
This project consisted of painting the steel surfaces of a 60-ft diameter digester at the Wastewater Treatment Facility.  This work included the removal of sludge and cleaning of the digester, removal of the existing paint, re-coating the interior and exterior steel surfaces of the digester including all exposed parts and all other appurtenances.  Three valve replacements were included while the digesters were out of service.  During the course of construction, it was determined that the primary digester lid is beyond its useful service life.  Replacement of this lid will be budgeted in FY 20/21.
ACTUAL COST VS. BUDGET:

There were five (5) change orders associated with this project that decreased the contract by $4,800.37, from the original amount of $475,538.24.

 

Change Order Description Contract Days Added Force Account Amount Contract Amount
1 Steel seam filler of angle iron around Secondary Digester lid 2 $ 4,462.50
2 Sandblast, coat, and install wheels 2 $ 3,150.00
3 Additional scaffolding (Secondary Digester) 5 $ 11,025.00
4 Additional scaffolding (Primary Digester) sandblast and coat pipe and fittings on lid 7 $ 11,362.50 $ 6,497.50
5 Additional crane work Final quantity adjustments 1 $ (11,297.87)
Total 17 $ 30,000.00 $ (4,800.37)

 

Funds were appropriated from the Sewer Fund, Budget Account 505-70-75-443-40-44320.

SUGGESTED MOTION:
I Move for Approval of the Acceptance of Public Improvements for the Wastewater Treatment Facility Anaerobic Digester Cleaning and Coating Project to R.C.S. Construction, Inc., of Rapid City, South Dakota, in the Amount of $470,737.87.  
STAFF REFERENCE:
VIDEO - Michael H. Cole, P.E., Utilities Director